Question: Question 3: Use the activity table below and execute the following: Draw a network Activity Predecessor Duration Resources per day A Start 4 36 B
Question 3:
Use the activity table below and execute the following:
- Draw a network
-
Activity
Predecessor
Duration
Resources per day
A
Start
4
36
B
A
6
30
C
A
8
45
D
A
5
20
E
B
6
15
F
B,C
8
25
G
D
3
12
H
E
8
22
I
F
5
32
J
C,G
5
25
K
I
8
20
L
J,K
6
28
M
H,L
4
30