Question: QUESTION 3 Using the information below, calculate the net savings of shortening the project to its minimum length. The indirect costs per day are 615

QUESTION 3 Using the information below, calculate

QUESTION 3 Using the information below, calculate the net savings of shortening the project to its minimum length. The indirect costs per day are 615 Activity Predecessor Normal Time (days) Crashing Time (days) Crashing Cost / Day. A 5 1 215 B 7 1 500 5 1 200 10 393 E F AC 2 650 4 500 E,D,G 384 A 2 B 6 1 400 7 G B 1 H 6 1