Question: Question 3 What does PERT stand for?In a given project, the most optimistic duration is 2 days, most likely duration is 3 daysand the pessimistic

Question 3What does PERT stand for?In a given project, the most optimistic duration is 2 days, most likely duration is 3 daysand the pessimistic duration is 10 days. What is the PERT weighted average?