Question 31 A manual assembly line with a work content time =50min. The line will be operated 20.000 hr /yr. The annual demand anticipated for the product is 100,000 units. Based on previous assembly lines used by the company, the proportion of uptime on the line is expected to be 94%, the line balancing efficiency will be 92%. The line will be designed with 1 worker/station. Determine the ideal minimum number of workers required Select one: a. 45 worker b. 4 workers c. 5 workers d. 44 workers Clear my choice