Question: QUESTION 32 We have the following project, including task length and predecessors for each task: Task Completion Predecessor Time 2 - A B 5 -

QUESTION 32 We have the following project,
QUESTION 32 We have the following project, including task length and predecessors for each task: Task Completion Predecessor Time 2 - A B 5 - 4 A D 6 AB 3B E F 7 C G 5D If we spend $6000 per week in labor costs, how much do we expect to spend in labor for this project