Question: We have the following project, including task length and predecessors for each task: Task Completion Time Predecessor A 2 - B 5 - C 4
We have the following project, including task length and predecessors for each task:
| Task | Completion Time | Predecessor |
| A | 2 | - |
| B | 5 | - |
| C | 4 | A |
| D | 6 | A,B |
| E | 3 | B |
| F | 7 | C |
| G | 5 | D |
If we spend $6000 per week in labor costs, how much do we expect to spend in labor for this project?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts