Question: Question 33 1.5 pts Project management process used to determine if it makes sense to increase costs to save time is referred to as: O

Question 33 1.5 pts Project management process

Question 33 1.5 pts Project management process used to determine if it makes sense to increase costs to save time is referred to as: O B. Fast Tracking OC. Activity Crashing O D. Project Accelerating O E. Activity Expediting