Question: QUESTION 35 For an activity in a PERT network, the most reasonable time is 126 days, the expected time is 122 days, and the shortest

QUESTION 35 For an activity in a PERT network,
QUESTION 35 For an activity in a PERT network, the most reasonable time is 126 days, the expected time is 122 days, and the shortest possible time is 100 days. Find the longest possible time of this activity. 0 128 135.75 125.5 246