Question: A Moving to another question will save the response. Question 23 For an activity in a PERT network, the longest possible time is 108 days,

A Moving to another question will save the
A Moving to another question will save the response. Question 23 For an activity in a PERT network, the longest possible time is 108 days, the expected time is 98 days, and the shortest possible time is 80 days. Find the most reasonable time of this activity. O A. 135.75 OB. 100 OC. 51 D. 128 hp