Question: QUESTION 36 Answer the next 4 questions from the network and its activities shown below: Activity Duration Immediate Days Predecessors A 4 --- B 2

QUESTION 36

  1. Answer the next 4 questions from the network and its activities shown below:

    Activity

    Duration

    Immediate

    Days

    Predecessors

    A

    4

    ---

    B

    2

    A

    C

    7

    --

    D

    4

    A

    E

    5

    B,C,D

    The critical activities are:

    a.

    A-B-D

    b.

    A-B-E

    c.

    C-E

    d.

    A-D-E

    e.

    A-B-C-D-E

1 points

QUESTION 37

  1. From the information above, the earliest project completion time is:

    a.

    10 days

    b.

    11

    c.

    12

    d.

    13

    e.

    22

1 points

QUESTION 38

  1. From the information above, the Activity with the most slack is:

    a.

    Activity A

    b.

    B

    c.

    C

    d.

    D

    e.

    E

1 points

QUESTION 39

  1. Again, from the previous information, the Latest Starting time of Activity C is:

    a.

    Right Now

    b.

    1 day

    c.

    2

    d.

    5

    e.

    7

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!