Question: QUESTION 36 Answer the next 4 questions from the network and its activities shown below: Activity Duration Immediate Days Predecessors A 4 --- B 2
QUESTION 36
-
Answer the next 4 questions from the network and its activities shown below:
Activity
Duration
Immediate
Days Predecessors
A
4
---
B
2
A
C
7
--
D
4
A
E
5
B,C,D
The critical activities are:
a. A-B-D
b. A-B-E
c. C-E
d. A-D-E
e. A-B-C-D-E
1 points
QUESTION 37
-
From the information above, the earliest project completion time is:
a. 10 days
b. 11
c. 12
d. 13
e. 22
1 points
QUESTION 38
-
From the information above, the Activity with the most slack is:
a. Activity A
b. B
c. C
d. D
e. E
1 points
QUESTION 39
-
Again, from the previous information, the Latest Starting time of Activity C is:
a. Right Now
b. 1 day
c. 2
d. 5
e. 7