Question: For the network activities shown below: Activity Duration Immediate Predecessors A 2 - - B 4 - - C 6 A , B D 1

For the network activities shown below:
Activity
Duration
Immediate
Predecessors
A 2--
B 4--
C 6 A,B
D 1 A,B
E 2 B,C,D
Activity D and E has zero slack time. True or false