Question: QUESTION 39 BA contributes by creating and updating models that do all except: Depict the business Describe the business operations Describe Governmental actions Represent the
QUESTION 39
-
BA contributes by creating and updating models that do all except:
Depict the business
Describe the business operations
Describe Governmental actions
Represent the business and organizational structure
2 points
QUESTION 40
-
It is important to understand the organization. Which of the following is not a way to do this:
Shadow key stakeholders
Ask questions
Listen
Learn
All are way to do this
2 points
QUESTION 41
-
Components that will help the BA track business analysis risk include _____________: this element is typically a function of the impact and likelihood. Typically, the impact level and likelihood are multiplied to determine the risk level. When using low, medium, and high, for example these could be weighted as low equals one, medium equals two, and high equals three. Then if a risk had likelihood of medium and an impact of high it would be 23 = 6.
Risk level (exposure)
Risk response owner
Treatment
Risk remaining
2 points
QUESTION 42
-
Common estimation approaches include __________________: each component of the estimate is giving three values: optimistic value representing the best-case scenario, pessimistic value representing the worst case scenario, and the most likely value.
Delphi
Program evaluation and review technique (PERT)
ROM
rolling wave
2 points
QUESTION 43
-
A benefit from business analysis planning includes establishing a business analysis stakeholder engagement agreement to include how business analysis information will be communicated and the frequency to be expected by the stakeholders.
True
False
2 points
QUESTION 44
-
Components that will help the BA track business analysis risk include __________: this element is a description of the uncertain condition (risk). A risk could be one occurrence, several occurrences, or even a non-occurrence.
Treatment
Identified risk
Identified risk
Likelihood
2 points
QUESTION 45
-
Based on the cost of requirement errors and rework, spending more time on _________ can actually quicken solution deliverable should the requirements be correct at the right time the first time.
elaboration
change
requirements
risks
2 points
QUESTION 46
-
A leading cause of project failure is lack of ________. By obtaining stakeholder approval of the business analysis communication plan, the BA can be assured that the stakeholders understand the level of effort that will be required for project success, along with the intention of the business analysis work effort.
stakeholder buy-in
BA continuity
user input
resources
2 points
QUESTION 47
-
Components that will help the BA track business analysis risk include _____________: this element describes the outcome should the risk occur. One risk may have several consequences that must be considered.
Trigger
Consequence
Likelihood
Identified risk
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
