Question: QUESTION 39 BA contributes by creating and updating models that do all except: Depict the business Describe the business operations Describe Governmental actions Represent the

QUESTION 39

  1. BA contributes by creating and updating models that do all except:

    Depict the business

    Describe the business operations

    Describe Governmental actions

    Represent the business and organizational structure

2 points

QUESTION 40

  1. It is important to understand the organization. Which of the following is not a way to do this:

    Shadow key stakeholders

    Ask questions

    Listen

    Learn

    All are way to do this

2 points

QUESTION 41

  1. Components that will help the BA track business analysis risk include _____________: this element is typically a function of the impact and likelihood. Typically, the impact level and likelihood are multiplied to determine the risk level. When using low, medium, and high, for example these could be weighted as low equals one, medium equals two, and high equals three. Then if a risk had likelihood of medium and an impact of high it would be 23 = 6.

    Risk level (exposure)

    Risk response owner

    Treatment

    Risk remaining

2 points

QUESTION 42

  1. Common estimation approaches include __________________: each component of the estimate is giving three values: optimistic value representing the best-case scenario, pessimistic value representing the worst case scenario, and the most likely value.

    Delphi

    Program evaluation and review technique (PERT)

    ROM

    rolling wave

2 points

QUESTION 43

  1. A benefit from business analysis planning includes establishing a business analysis stakeholder engagement agreement to include how business analysis information will be communicated and the frequency to be expected by the stakeholders.

    True

    False

2 points

QUESTION 44

  1. Components that will help the BA track business analysis risk include __________: this element is a description of the uncertain condition (risk). A risk could be one occurrence, several occurrences, or even a non-occurrence.

    Treatment

    Identified risk

    Identified risk

    Likelihood

2 points

QUESTION 45

  1. Based on the cost of requirement errors and rework, spending more time on _________ can actually quicken solution deliverable should the requirements be correct at the right time the first time.

    elaboration

    change

    requirements

    risks

2 points

QUESTION 46

  1. A leading cause of project failure is lack of ________. By obtaining stakeholder approval of the business analysis communication plan, the BA can be assured that the stakeholders understand the level of effort that will be required for project success, along with the intention of the business analysis work effort.

    stakeholder buy-in

    BA continuity

    user input

    resources

2 points

QUESTION 47

  1. Components that will help the BA track business analysis risk include _____________: this element describes the outcome should the risk occur. One risk may have several consequences that must be considered.

    Trigger

    Consequence

    Likelihood

    Identified risk

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!