Question: Question 4 0 1 p t s A project being analyzed by PERT has 3 8 activities, 1 6 of which are on the critical

Question 4
01pts
A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critical path is 90 days with a project variance of 25, the probability that the project will be completed in 88 days or less is
0.0228
0.3446
0.6554
0.9772