Question: Question 4 1 1 0 pts The estimating factor that considers the tendency to overestimate project time and cost in order to improve the likelihood

Question 41
10 pts
The estimating factor that considers the tendency to overestimate project time and cost in order to improve the likelihood of meeting the estimates is known as the factor.
project complexity
padding estimates
organizational culture
planning horizon
people
 Question 41 10 pts The estimating factor that considers the tendency