Question: The estimating factor that considers the tendency to overestimate project time and cost in order to improve the likelihood of meeting the estimates is known

The estimating factor that considers the tendency to overestimate project time and cost in order to improve the likelihood of meeting the estimates is known as the factor.
project complexity
planning horizon
people
organizational culture
padding estimates
The information necessary to conduct a bottom-up estimate of project time and cost starts with the
level 4 elements of the WBS
milestones
work package
planning horizon
level 5 elements of the PBS
The information necessary to conduct a bottom-up estimate of project time and cost starts with the
level 4 elements of the WBS
milestones
work package
planning horizon
level 5 elements of the PBS
 The estimating factor that considers the tendency to overestimate project time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!