Question: Question 4 (1 point) The following table shows the durations and interdependencies of the activities of a project: Activity Duration (days) Immediate predecessor A 3

Question 4 (1 point) The following table shows
Question 4 (1 point) The following table shows the durations and interdependencies of the activities of a project: Activity Duration (days) Immediate predecessor A 3 B 5 A 2 B D 3 A E 8 BD Activity E can be delayed/prolonged by up to ___ days without increasing the project duration (Fill in blank with a nonnegative number) Your