Question: Question 13 (1 point) The following table shows the durations and interdependencies of the activities of a project: Activity Duration (days) Immediate predecessor 3 B

Question 13 (1 point) The following table shows
Question 13 (1 point) The following table shows the durations and interdependencies of the activities of a project: Activity Duration (days) Immediate predecessor 3 B 5 2 B D 23 A E 8 B.D Activity E can be delayed/prolonged by up to days without increasing the project duration (Fill in blank with a nonnegative number) Your