Question: QUESTION 4 ( 2 0 Marks ) The table below gives the duration estimates in days for a construction projection. table [ [ Activity

QUESTION 4
(20 Marks)
The table below gives the duration estimates in days for a construction projection.
\table[[Activity,Predecessor,Optimistic,Most Likely,Pessimistic],[A,-,2,4,7],[B,-,1,3,6],[C,-,3,5,8],[D,A,9,11,20],[E,A,2,5,7],[F,B,6,10,20],[G,E, F,3,7,12],[H,D,4,9,13],[I,G,6,4,6],[J,H,J,3,10,23],[K,I,K,7,,9],[L,,,,]]
4.1 Determine the expected completion time for each activity. Round off answers to the nearest whole
(5 marks)
number.
4.2 Construct an Activity-on-node (AON) network for the activities of this contract.
(5 marks)
4.3 Determine the critical path for the project by calculating the slack for each activity.
(10 marks)
 QUESTION 4 (20 Marks) The table below gives the duration estimates

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!