Question: QUESTION 4 [ 2 5 ] The following data relates to a project that you are managing: Time in days Activity Predecessor Optimistic ( a
QUESTION The following data relates to a project that you are managing: Time in days Activity Predecessor Optimistic a Most likely m Pessimistic b A B A C A D A E B F C;D G E H E I F;H J G;H K I;J Using the PERT formula, calculate the time t and variance for all activities. Construct the network diagram AON and identify all paths and show the critical path. Calculate the probability of completing this project within days.