Question: QUESTION 4 [ 2 5 ] The following data relates to a project that you are managing: Time in days Activity Predecessor Optimistic ( a

QUESTION 4[25] The following data relates to a project that you are managing: Time in days Activity Predecessor Optimistic (a) Most likely (m) Pessimistic (b) A -6815 B A 151622 C A 5812 D A 101218 E B 121723 F C;D 141621 G E 161819 H E 51014 I F;H 369 J G;H 81317 K I;J 711154.1 Using the PERT formula, calculate the time (t) and variance for all activities. (5)4.2 Construct the network diagram (AON) and identify all paths and show the critical path. (10)4.3 Calculate the probability of completing this project within 80 days. (5)