Question: Question 4 ( 2 points ) What input should be used in project initiation processes? Communication plan, stakeholder management plan. Industry standards, list of vendors.

Question 4(2 points)
What input should be used in project initiation processes?
Communication plan, stakeholder management plan.
Industry standards, list of vendors.
List of risks, risk management plan, risk audit.
Historical information, company change control system, industry standards.