Question: QUESTION 4 4.1 REQUIRED Use the information provided below to calculate the overhead costs per unit for each product using activity-based costing INFORMATION Remax Inc
QUESTION 4
4.1 REQUIRED
Use the information provided below to calculate the overhead costs per unit for each product using activity-based costing
INFORMATION
Remax Inc produces two products viz A and B. The same equipment is used to produce both products.
Details of the cost of activities, inputs and outputs are as follows:
Overheads cost analysis:
|
| R |
| Materials handling | 540 000 |
| Materials procurement | 180 000 |
| Set-up | 540 000 |
| Quality control | 900 000 |
| Production | 2 160 000 |
|
| 4 320 000 |
Cost driver analysis
| Overheads | Cost drivers | Product A | Product B | Total |
| Materials handing | Materials movements | 360 | 180 | 540 |
| Materials procurement | Number of orders | 640 | 360 | 1000 |
| Set-up | Number of set-ups | 216 | 144 | 360 |
| Quality control | Number of inspections | 540 | 360 | 900 |
| Production | Direct labour hours | 144 000 | 36 000 | 180 000 |
Annual output
| Product A | 144 000 units |
| Product B | 36 000 units |
4.2 REQUIRED
Calculate the following from the information given below:
4.2.1 Break even quantity (4)
4.2.2 The number of units that must be sold to obtain a net profit of R300 000 (4)
4.2.3 Break-even quantity, if the selling price is reduced by R20 per unit (4)
INFORMATION
The following per unit projected for a product that is the output of Project M is provided below:
| Selling price | R400 |
| Direct materials | R140 |
| Direct labour | R60 |
| Variable manufacturing overheads | R40 |
Fixed manufacturing overheads are expected to amount to R560 000. Projected administration and marketing costs comprise the following:
- Fixed costs R400 000
- Sales commission of 10%
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
