Question: Question 4 ( 6 points ) : For the following real - time processes, draw the Gantt chart, calculate the CPU utilization and decide whether

Question 4(6 points): For the following real-time processes, draw the Gantt chart, calculate the
CPU utilization and decide whether the two processes would miss their deadlines or not using Rate
Monotonic (RM) and Earliest Deadline First (EDF) algorithms.
P1: Period =75, Processing Time =35
P2: Period =40, Processing Time =20
 Question 4(6 points): For the following real-time processes, draw the Gantt