Question: Question 4 ( a ) Your organization is awarded a Fixed Price Incentive contract for the design and build of a large manufacturing facility for

Question 4
(a) Your organization is awarded a Fixed Price Incentive contract for the design
and build of a large manufacturing facility for multinational pharmaceutical
company ECOT Ltd. Using the information provided in Table Q4, calculate
profit to your organisation and the price that ECOT Ltd will pay? Based on
your calculations, assess this type of contract.
Table Q4
[6 marks]
(b) Claims and disputes can have a major impact on all aspects of project
performance and quality.
(i) Reflect on key actions a responsible client should take to minimise
claims in a project.
(ii) Discuss the important features of five mechanisms for dispute
resolution.
[6 marks]
(c) Quality means conformance to requirements. Your company was recently
awarded a large design and build contract for a storm water sewer network
and you are assigned to define the quality of sewer pipes. It is required that
the sewer lines will be constructed from pre-cast concrete hume pipes. For
this material, define the quality characteristics and quality of design.
[8 marks]
Question 4 ( a ) Your organization is awarded a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!