Question: Question 4 - Calculate the Schedule Performance Index (SPI) and the Cost Performance Index (CPI) based on BCWS and BCWP. Based on these calculations, determine

 Question 4 - Calculate the Schedule Performance Index (SPI) and the

Question 4 - Calculate the Schedule Performance Index (SPI) and the Cost Performance Index (CPI) based on BCWS and BCWP. Based on these calculations, determine if the project is ahead or behind schedule and if the cost is under or over budget? SPI = BCWP / BCWS CPI = BCWP / ACWP Activity 30 - Super Substructure SPI = CPI = Ahead or Behind Schedule? Under or Over Budget? Activity 50 = Interior