Question: Question #4 Consider the same batch flow process as above but now Step 3 also has a setup time. Step 1 Step 2 Step 3
Question #4
Consider the same batch flow process as above but now Step 3 also has a setup time.
| Step 1 | Step 2 | Step 3 | |
| Processing time | 2 mins/unit | 3 mins/unit | 1.5 mins/unit |
| Setup Time | 20 mins | No setup | 40 mins |
What is the ideal batch size (i.e. one that minimizes inventory without affecting process capacity)?
DEMAD RATE= d/timeperiod =60/1= 60 unites per hour
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock