Question: Question 4 e,f begin{tabular}{|c|c|c|c|c|c|} hline Activity & Predecessors & Estimated Duration (day) & Normal Cost (RM) & Crashed Duration (day) & Crashed Cost (RM)


Question 4 e,f
\begin{tabular}{|c|c|c|c|c|c|} \hline Activity & Predecessors & Estimated Duration (day) & Normal Cost (RM) & Crashed Duration (day) & Crashed Cost (RM) \\ \hline A & & 8 & 4,000 & 6 & 5,800 \\ \hline B & A & 8 & 3,800 & 5 & 4,200 \\ \hline C & A & 6 & 3,500 & 5 & 4,000 \\ \hline D & B & 4 & 4,300 & 3 & 4,800 \\ \hline E & C & 5 & 2,800 & 4 & 3,400 \\ \hline F & C & 7 & 3,200 & 5 & 3,800 \\ \hline G & D. E & 10 & 5,400 & 8 & 6,000 \\ \hlineH & F. G & 5 & 4,200 & 4 & 5,200 \\ \hline \end{tabular} What is the new total project duration and new total project cost after the crashing activity? (show your calculation). (22 Marks) Briefly explain ONE (1) fundamental thing the project manager should consider before proceeding with the project crashing decision. (2 Marks)Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
