Question: Question 4 Given the activity time estimates below, what is the expected time for Activity A? (round to 2 decimals as needed) Not yet answered

Question 4 Given the activity time estimates

Question 4 Given the activity time estimates below, what is the expected time for Activity A? (round to 2 decimals as needed) Not yet answered Activity Optimistic Time Most Likely Time Pessimistic Time Marked out of 1.00 A 2.0 5.8 7.0 P Flag question B 2.0 4.1 4.1 1.0 1.9 6.0 D 5.9 6.9 8.0 Select one: a. 4.60 o b. 2.47 c. 2.43 d. 6.92 e. 3.75 f. 5.37 g. None of the other options. h. 4.93