Question: Given the activity time estimates below, what is the expected time for Activity A? (round to 2 decimals as needed) Given the activity time estimates

Given the activity time estimates below, what is the expected time for Activity A? (round to 2 decimals as needed)
Given the activity time estimates below, what is the variance for Activity B? (round to 4 decimals as needed)
Given the activity time estimates below, what is the expected time for Activity A? (round to 2 decimals as needed) Activity Optimistic Time Most Likely Time Pessimistic Time A 1.9 6.0 7.1 B 1.8 4.0 4.0 1.0 1.9 6.1 D 6.1 6.8 7.8Step by Step Solution