Question: 1. Given the activity time estimates below, what is the expected time for Activity D? (round to 2 decimals as needed) Activity Optimistic Time Most
1. Given the activity time estimates below, what is the expected time for Activity D? (round to 2 decimals as needed)
| Activity | Optimistic Time | Most Likely Time | Pessimistic Time |
| A | 1.9 | 5.9 | 7.2 |
| B | 2.1 | 4.1 | 4.1 |
| C | 1.0 | 2.0 | 6.1 |
| D | 5.9 | 6.8 | 7.9 |
Select one:
A. 3.43
B. 3.77
C. 5.45
D. 2.52
E. 6.83
F. 5.19
G. None of the other options.
H. 6.87
2. An activity in a network diagram has an optimistic time estimate of five days, a most likely time estimate of seven days, and a pessimistic time estimate of 15 days. Its expected time is ____ days.
3. What is the likelihood that the project described in the following table will be completed within 44 days?
| Activity | Optimistic | Most Likely | Pessimistic | Mean | Variance | Predecessor |
| A | 5 | 8 | 11 | None | ||
| B | 6 | 8 | 10 | A | ||
| C | 8 | 13 | 16 | A | ||
| D | 4 | 5 | 8 | B, C | ||
| E | 9 | 12 | 15 | D | ||
| F | 10 | 15 | 20 | D |
You need to calculate Mean and Variance.