Question: 1. Given the activity time estimates below, what is the expected time for Activity D? (round to 2 decimals as needed) Activity Optimistic Time Most

1. Given the activity time estimates below, what is the expected time for Activity D? (round to 2 decimals as needed)

Activity

Optimistic Time

Most Likely Time

Pessimistic Time

A

1.9

5.9

7.2

B

2.1

4.1

4.1

C

1.0

2.0

6.1

D

5.9

6.8

7.9

Select one:

A. 3.43

B. 3.77

C. 5.45

D. 2.52

E. 6.83

F. 5.19

G. None of the other options.

H. 6.87

2. An activity in a network diagram has an optimistic time estimate of five days, a most likely time estimate of seven days, and a pessimistic time estimate of 15 days. Its expected time is ____ days.

3. What is the likelihood that the project described in the following table will be completed within 44 days?

Activity Optimistic Most Likely Pessimistic Mean Variance Predecessor
A 5 8 11 None
B 6 8 10 A
C 8 13 16 A
D 4 5 8 B, C
E 9 12 15 D
F 10 15 20 D

You need to calculate Mean and Variance.

Select one:

a. 44

b. 1.225

c. 6

d. 0.39

e. 0.11

f. 0.89

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!