Question: Question 4 ( Marks: 2 0 ) Given the following project activities, their predecessors, duration, and resource estimates answer the following questions: table [
Question
Marks:
Given the following project activities, their predecessors, duration, and resource estimates answer the following questions:
tableActivity Number,PredecessorsDuration DaysResources PeopleABACADB CEDHF G
Q Draw a graph of the resource loading for this project based on the earliest start
times of the activities. Graph does not need to be correctly scaled but must clearly show resource levels, fluctuations, and durations of usage
Q Without extending the project duration, draw a graph of the levelled resource
loading Minimise resource usage and fluctuations Briefly explain why the levelled resource loading diagram makes sense and list the activities that were affected and how the overall resource loading has changed along with why certain activities should not be moved regarding resource load levelling.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
