Question: Question 4 Match the term to the correct definition: The earliest time that an activity can start as determined by the latest of the early

Question 4
Match the term to the correct definition:
The earliest time that an activity can start as determined by the latest of the early finish times of all IPAs (immediately preceding activities)
The process of making network calculations starting from the first activity across through the last activity (used in finding the early starts and early finishes).
The latest time that an activity can start without delaying the project completion. It can be determined by subtracting the duration of the activity from its late finish:
The earliest time that an activity can finish. It is determined by adding the duration of the activity to the early start time of that activity.
The amount of time that an activity can be delayed before it impacts the completion date of the entire project. Its Computations are simplified by setting this component of the last activity in the network to "0"(zero).
[ Choose ]
Total Float (TF)
Free Float
Late Activity Finish
Early Activity Finish (EF)
Forward Pass
LAG
Backward Pass
Late Activity Start (LS)
Start to Start
Early Activity Start (ES)
Finish to Start
 Question 4 Match the term to the correct definition: The earliest

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!