Question: Question 4 Match the term to the correct definition: The earliest time that an activity can start as determined by the latest of the early
Question
Match the term to the correct definition:
The earliest time that an activity can start as determined by the latest of the early finish times of all IPAs immediately preceding activities
The process of making network calculations starting from the first activity across through the last activity used in finding the early starts and early finishes
The latest time that an activity can start without delaying the project completion. It can be determined by subtracting the duration of the activity from its late finish:
The earliest time that an activity can finish. It is determined by adding the duration of the activity to the early start time of that activity.
The amount of time that an activity can be delayed before it impacts the completion date of the entire project. Its Computations are simplified by setting this component of the last activity in the network to zero
Choose
Total Float TF
Free Float
Late Activity Finish
Early Activity Finish EF
Forward Pass
LAG
Backward Pass
Late Activity Start LS
Start to Start
Early Activity Start ES
Finish to Start
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock