Question: QUESTION 4 The earliest finish time for an activity a . is calculated by adding the activity's estimated duration to its earliest start time. b
QUESTION
The earliest finish time for an activity
a is calculated by adding the activity's estimated duration to its earliest start time.
b is the same as the earliest start time of the activity's predecessor.
c is dependent upon the start time of its successor activities.
d should not be delayed or would cause the project to be delayed.