Question: QUESTION 4 The earliest finish time for an activity a . is calculated by adding the activity's estimated duration to its earliest start time. b

QUESTION 4
The earliest finish time for an activity
a. is calculated by adding the activity's estimated duration to its earliest start time.
b. is the same as the earliest start time of the activity's predecessor.
c. is dependent upon the start time of its successor activities.
d. should not be delayed or would cause the project to be delayed.
 QUESTION 4 The earliest finish time for an activity a. is

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!