Question: We suppose that the Duration given time is the Optimistic time, that the Pessimistic time is 2 days more than each Optimistic time, and that

We suppose that the Duration given time is theWe suppose that the Duration given time is the Optimistic time, that the Pessimistic time is 2 days more than each Optimistic time, and that the Most Likely time is given in the table below: Most Likely Activity Time (Days) A 7 B 2 C 3.5 D 5.5 E 4 F 3 G 3 H 4.5 I 4 J 3.5 4) Determine the Expected Time for each activity (1pt) 5) Calculate the standard deviation of the project duration (1pt) 6) Determine the probability that the project is completed within 20 days (1pt)

We suppose that the Duration given time is the Optimistic time, that the Pessimistic time is 2 days more than each Optimistic time, and that the Most Likely time is given in the table below: Most Likely Activity Time (Days) A 7 B 2 3.5 D 5.5 E 4 F 3 G 3 H 4.5 I 4 J 3.5 4) Determine the Expected Time for each activity (1pt) 5) Calculate the standard deviation of the project duration (1pt) 6) Determine the probability that the project is completed within 20 days (1 pt) We suppose that the Duration given time is the Optimistic time, that the Pessimistic time is 2 days more than each Optimistic time, and that the Most Likely time is given in the table below: Most Likely Activity Time (Days) A 7 B 2 3.5 D 5.5 E 4 F 3 G 3 H 4.5 I 4 J 3.5 4) Determine the Expected Time for each activity (1pt) 5) Calculate the standard deviation of the project duration (1pt) 6) Determine the probability that the project is completed within 20 days (1 pt)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!