Question: We suppose that the Duration given time is the Optimistic time, that the Pessimistic time is 2 days more than each Optimistic time, and that
We suppose that the Duration given time is the Optimistic time, that the Pessimistic time is 2 days more than each Optimistic time, and that the Most Likely time is given in the table below: Most Likely Activity Time (Days) A 7 B 2 C 3.5 D 5.5 E 4 F 3 G 3 H 4.5 I 4 J 3.5 4) Determine the Expected Time for each activity (1pt) 5) Calculate the standard deviation of the project duration (1pt) 6) Determine the probability that the project is completed within 20 days (1pt)