Question: QUESTION 47 What is the likelihood that the project described in the following table will be completed within 44 days, if the critical path
QUESTION 47 What is the likelihood that the project described in the following table will be completed within 44 days, if the critical path is A-C-D-F? Optimistic Most Likely Pessimistic Variance Activity A Predecessor 5 11 1 None B 6 10 0.44 A C 8 16 1.78 A D 4 8 0.44 B, C 15 1 D 20 2.78 E F 0.89 0.74 0.79 0.84 0.99 9 10 8 8 13 5 12 15 Mean 8 8 12.66 5.33 12 15 D
Step by Step Solution
There are 3 Steps involved in it
To determine the likelihood that the project will be completed within 44 days we need to calculate t... View full answer