Question: Question 5 (15 points, plus 10-point bonus questions) Table 4 A) Using Table 4, what is the earliest expected completion time of the whole project?

Question 5 (15 points, plus 10-point bonus
Question 5 (15 points, plus 10-point bonus questions) Table 4 A) Using Table 4, what is the earliest expected completion time of the whole project? B) If the project is due to be completed in 21 days, using Table 4 , what is the probability that the project will be completed on or before the due date? C) Using both Table 3 and Table 4 . What is the sequence that activities to be crashed to achieve the least cost objective? D) Following Question 20), assume that the pessimistic times for all activities you just crashed in Question 20) are one week more than the most-likely times after crashing. What is the probability that the project will be completed on or before the due date? E) Simply using Table 4 , if the project manager wants at least a 95% probability that the project will be completed on or before the due date, what is the shortest project due date that will satisfy the manager? Question 5 (15 points, plus 10-point bonus questions) Table 4 A) Using Table 4, what is the earliest expected completion time of the whole project? B) If the project is due to be completed in 21 days, using Table 4 , what is the probability that the project will be completed on or before the due date? C) Using both Table 3 and Table 4 . What is the sequence that activities to be crashed to achieve the least cost objective? D) Following Question 20), assume that the pessimistic times for all activities you just crashed in Question 20) are one week more than the most-likely times after crashing. What is the probability that the project will be completed on or before the due date? E) Simply using Table 4 , if the project manager wants at least a 95% probability that the project will be completed on or before the due date, what is the shortest project due date that will satisfy the manager

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!