Question: Question 5 6 pts Project Planning: Critical Path 4 2 B A D E 6 What is the Critical Path (answer format is WXYZ)? How

Question 5 6 pts Project Planning: Critical Path 4 2 B A D E 6 What is the Critical Path (answer format is WXYZ)? How many days is the critical path (answer format is a single integer)? What is the float for activity D (answer format is a single integer)? Note: Sometimes the automated grading doesn't recognize the format of correct answers. I will review all wrong answers to see if any correct responses are missed
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
