Question: Question 5 (a) Given in Table 5 below are 6 jobs together with their respective processing times in days and due dates that are to

Question 5 (a) Given in Table 5 below are 6 jobs
Question 5 (a) Given in Table 5 below are 6 jobs together with their respective processing times in days and due dates that are to be processed in a single machine 6 Table 5: Processing and Due Dates Jobs 1 2 3 4 Processing Times (days) 21.4 5.7 16.2 8.4 Due Dates 25 34 82 54 5 9.0 11.2 70 45 Determine the sequence of jobs to be processed and the average lateness using the following priority rule: Shortest Processing Time (SPT) i. ii. Earliest Due Date (EDD)