Question: Question (5): Construct an activity-on-branch network from the precedence relationships of activities in the project given in the following table: A B C D
Question (5): Construct an activity-on-branch network from the precedence relationships of activities in the project given in the following table: A B C D E F G H I J K --- --- --- A B B C C D,E F,G H 5 1 1 7 6 4 3 6 4 3 Activity Predecessors Duration (days) 3 a- Determine the critical path. b- Determine the completion time of the project. c- Set a table to determine the free, independent, and total float d- Draw the Time Scaled Network Diagram.