Question: Question (5 points) Consider the following project. Create a basic Gantt chart using MS Excel for the project schedule. Hint: Refer to Video #4. Activity

Question (5 points)

Consider the following project. Create a basic Gantt chart using MS Excel for the project schedule. Hint: Refer to Video #4.

ActivityDuration in daysStart DateTask A171-AugustTask B915-AugustTask C1420-AugustTask D121-SeptemberTask E1922-SeptemberTask F525-SeptemberTask G1728-SeptemberTask H105-OctoberTask I58-October