Question: Consider the following project. Create a basic Gantt chart using MS Excel for the project schedule. Activity Duration in days Start Date Task A 17
Consider the following project. Create a basic Gantt chart using MS Excel for the project schedule.
| Activity | Duration in days | Start Date |
| Task A | 17 | 1-August |
| Task B | 9 | 15-August |
| Task C | 14 | 20-August |
| Task D | 12 | 1-September |
| Task E | 19 | 22-September |
| Task F | 5 | 25-September |
| Task G | 17 | 28-September |
| Task H | 10 | 5-October |
| Task I | 5 | 8-October |