Question: Question 5: Project Network Draw a project network from the following information. What activity(s) is a burst activity? What activity(s) is a merge activity? ID

Question 5: Project Network Draw a project
Question 5: Project Network Draw a project network from the following information. What activity(s) is a burst activity? What activity(s) is a merge activity? ID Description Predecessor A Survey site None B Excavate site A Install power lines B 20 D Install drainage B E Pour foundation CD