Question: QUESTION 5 The CV for this project is: PV = $2,200, EV = $2,000, AC = $2,500, BAG = $10,000 $300 -$300 $500 -$500
QUESTION 5
The CV for this project is:
PV = $2,200, EV = $2,000, AC = $2,500, BAG = $10,000
$300
-$300
$500
-$500