Question: Question 6 (1 point) A certain process measurement has a mean of 29 and a standard deviation of 0.5. The specifications call for 30 +

Question 6 (1 point) A certain process
Question 6 (1 point) A certain process
Question 6 (1 point) A certain process measurement has a mean of 29 and a standard deviation of 0.5. The specifications call for 30 + 2. What is the value of the process capability index (Cpk? A) 2 B) 0.67 C) 1 D) 1.33 Question 8 (1 point) If the calculated value of Cpkis 1.6, we would conclude OA A) the process is in control. B) the process is NOT capable of consistently meeting the specs. C) the process is NOT in control. D) the process is capable of consistently meeting the specs