Question: QUESTION 6 (20 Marks) The table below gives the duration estimates in days for a construction projection. 6.1 Determine the expected completion time for each

QUESTION 6 (20 Marks) The table below gives the duration estimates in days for a construction projection. 6.1 Determine the expected completion time for each activity. Round off answers to the nearest whole number. (5 marks) 6.2 Construct an AON network for the activities of this contract. (5 marks) 6.3 Determine the critical path for the project by calculating the slack for each activity. (10 marks) END OF PAPER