Question: ust complete Part 1 first. Question 2 A project has 55 activities, but only 5 of them are analyzed in this problem Activity F, IP

ust complete Part 1 first. Question 2 A project
ust complete Part 1 first. Question 2 A project has 55 activities, but only 5 of them are analyzed in this problem Activity F, IP = not given Activity H, IP = not given Activity P, IP = not given Activity S, IP = F, H,P Activity V, IP = P The duration of activity F, H, and P are 13, 13, and 19 days, respectively. It has been calculated that LS(S) = 76 and LS(V) = 78. Find the value of LS(P). - Previous JUL 26 tv MacBC