Question: Question 6 ( Mandatory ) ( 1 0 points ) In a CPM analysis, if you subtract the early start from the late start, the
Question Mandatory points
In a CPM analysis, if you subtract the early start from the late start, the result is the activity's time.
wasted
productive
slack
online
experience