Question: Problem #1 20 Points Develop a CPM diagram for the activities/relationships listed below. For each activity calculate the Early Start, Late Start, Early Finish, Late

Problem #1 20 Points Develop a CPM diagram for
Problem #1 20 Points Develop a CPM diagram for the activities/relationships listed below. For each activity calculate the Early Start, Late Start, Early Finish, Late Finish, Total Float, and Free Float. Clearly identify the critical path for the project (hint: a highlighter would be a good tool to use) Activity Duration Immediately Following Activities 22 a b d e f 8 h 10 13 8 15 17 15 6 11 12 20 cf8 hik hik dj