Question: Question 6: Pert Chart (8 points) + 2 extra credits Extra Credit: If the entire class gets this question correct, I will add 2 extra

Question 6: Pert Chart (8 points) + 2 extra

Question 6: Pert Chart (8 points) + 2 extra credits Extra Credit: If the entire class gets this question correct, I will add 2 extra credits to each exam. This question has two parts. You are allowed to use the lecture notes and your notes to answer the question. No other materials are allowed. Question 6a: Mark the earliest start time and latest start time for each node. Question 6b: List the critical path(s). un -16 8 10 11 10 9 4 21 12 12 14 15 5 -20 8