Question: Consider the following project activities and their respective durations: Activity | Predecessor | Duration ( days ) A | - | 5 B | -

Consider the following project activities and their respective durations:
Activity | Predecessor | Duration (days)
A |-|5
B |-|3
C | A |4
D | A |6
E | B |2
F | B |4
G | C, D |5
H | E, F |3
I | G, H |7
Based on the given information, what is the critical path of the project?
Select one:
Critical Path: B - E - H - I; Total Duration: 12 days
Critical Path: B - F - H - I; Total Duration: 14 days
Critical Path: A - D - G - H - I; Total Duration: 23 days
Critical Path: A - C - G - I; Total Duration: 21 days