Question: Consider the following project activities and their respective durations: Activity | Predecessor | Duration ( days ) A | - | 5 B | -
Consider the following project activities and their respective durations:
Activity Predecessor Duration days
A
B
C A
D A
E B
F B
G C D
H E F
I G H
Based on the given information, what is the critical path of the project?
Select one:
Critical Path: B E H I; Total Duration: days
Critical Path: B F H I; Total Duration: days
Critical Path: A D G H I; Total Duration: days
Critical Path: A C G I; Total Duration: days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
