Question: Question 7 (1 point) The following table shows the durations, interdependencies and crash costs per day of the activities of a project. Suppose that the

Question 7 (1 point) The following table shows
Question 7 (1 point) The following table shows the durations, interdependencies and crash costs per day of the activities of a project. Suppose that the crash time of all activities are zero. Immediate Activity Duration (days) predecessor Crash cost per period A 2 2 $100 B 3 A $80 11 B $120 D 3 3 $300 E 7 CD $400 What is the slack of activity D? Your